Skip Ribbon Commands
Skip to main content
2018 - 2022 CIP Program Summary As of Mar 31, 2018
.
Project Name and Location RFP(1) Design(2) Award of Construction Construction Est.($M)
CIP Collection Systems (Interceptors - Rehab)
  CIP Collection System Systemwide        
Jennings/Dille Pump Stations Upgrades07-Jun-18N/A20-Sep-18$1.5
This project will provide D/B contract to perform various upgrades at the Dille Avenue and Jennings Avenue Pump Stations (PS). The pump station upgrades include replacement of existing electrical MCCs, work panelboards, transformers, interior/exterior lighting, emergency lighting, protective device study (including arc flash study and labelling) and replacement of the flow meter at each pump station. In addition, the work Dille Avenue PS includes an investigation to determine changes required to accommodate the changes to the MCC location to meet code compliance and painting the interior walls.
Barberton Creek Pump Station Upgrades02-Aug-18N/A01-Nov-18$1.5
The Barberton Pump Station was transferred to NEORSD from the City of Cleveland. NEORSD has made some minor modifications to the pump station. However, there is a need to evaluate replacement of major components and the need to meet current NFPA 820 standards, Ohio building code, National Electric code and Ten State Standards codes.
Odor Control Facility Upgrades3rd Quarter 20191st Quarter 20201st Quarter 2021$2.3
Reconfiguration and replacement of filter media at 7 locations with synthetic media that does not require reoccurring replacement every 3 years
Pump Stations and Auto Regulator R&R Projects (2019-2036)3rd Quarter 20214th Quarter 20214th Quarter 2022N/A
Pump Stations and Auto Regulator R&R Projects (2019-2036)
CSO Culvert Inspection and Repair 12nd Quarter 20213rd Quarter 20212nd Quarter 2022$24.6
This project is part of an ongoing inspection and repair program on CSO culverts in order to establish a baseline condition, determine if repairs are needed, then design and construct the repairs.
Collection System Asset Renewal-21st Quarter 20203rd Quarter 20202nd Quarter 2021$4.0
The CSAR projects will effectively prioritize collection system repair based off a menu of sewer segments that are expected to have reached the end of their useful lives. The menu was developed based on the District''''s asset management repair and renewal tool output. The CSAR-2 designers will review the list of choices and help us determine the sewer segments to inspect, design and repair. The designer will also help determine project packaging for the future CSAR contracts.
Collection System Asset Renewal-33rd Quarter 20214th Quarter 20214th Quarter 2022$4.0
Collection System Asset Renewal-42nd Quarter 20223rd Quarter 20222nd Quarter 2023$4.0
This project is based upon the years 2017-2020 repair and renewal plan output. This project''''s delivery method will potentially be a "find and fix" and/or "indefinite quantity" contract and the method will ultimately be determine during the IIEC-2 project in a workshop with District staff and the Consultant. Target pipes are attached in the Excel file.
Collection System Asset Renewal-54th Quarter 20221st Quarter 20234th Quarter 2023$8.0
  CIP Collection System Easterly        
Green Creek Culvert Repair4th Quarter 20211st Quarter 20222nd Quarter 2023$3.6
.
CIP Collection Systems (Interceptors - Rehab) Sub-program Total $53.5
.
CIP Combined Sewer Overflow Control Program (CSO)
  Easterly CSO Projects        
Doan Valley Relief and Consolidation Sewer17-Mar-16 A21-Jul-16 A07-Jun-18$15.9
The DVRCS project will construct approximately 4,800 lf of 48 to 72-inch sewer to control combined sewer overflows. The project will also provide surcharge relief to the Doan Valley Interceptor (DVI) system to meet the desired performance during the 5-year 6-hour rainfall event.
Dugway Regulators and Relief Sewers21-Apr-16 A18-Aug-16 A21-Jun-18$5.4
The Dugway Regulators & Relief Sewers (DRRS) project will be designed and constructed in order to meet specific CSO control requirements of Control Measure #6 as identified in Appendix 1 of the Consent Decree. When complete, the project will provide CSO control for the Typical Year storm events and flood relief up to the 5-year, 6-hour storm within the Dugway Interceptor system. The project generally consists of new and replacement regulator structures, a water quality structure, manholes, catch basins, an access shaft/jacking pit for trenchless construction, a receiving pit for trenchless construction, water main replacement and utility relocation, trenchless and open-cut sewer installation, geotechnical instrumentation, and an adit connection from an access shaft to the existing Heights Interceptor Sewer. The project is located at three sites that are located in Cleveland, East Cleveland, and Cleveland Heights, Ohio.
London Road Relief Sewer07-Jul-16 A17-Nov-16 A21-Jun-18$51.5
The London Road Relief Sewer (LRRS) project will provide surcharge relief for sewers tributary to the Ivanhoe-Holmes Branch Interceptor along Holmes Avenue and London Road, and intra-community relief sewers on Roseland Drive and Green Road. The project will also control combined sewer overflows to Green Creek and Nine Mile Creek. The project includes relief systems ranging from 18 to 84 inches in diameter with a total length of approximately 15,500 feet.
Doan Valley Regulators / Relief20-Oct-16 A16-Mar-17 A2nd Quarter 2019$9.0
The Doan Valley Regulators / Relief Sewers (DVRRS) project will be designed and constructed in order to meet specific CSO control requirements of Control Measure #8 as identified in Appendix 1 of the Consent Decree. When complete the project will provide CSO control for the Typical Year storm events and flood relief up to the 5-year, 6-hour storm within the Doan Valley Interceptor system. The project will provide open-cut sewer and storm pipe ranging from 18-inch to 72-inch, modifications at regulators, regulator reconstructions, and regulator abandonments.
Shoreline Storage Tunnel05-Apr-1804-Oct-181st Quarter 2021$203.7
The selected consultant will be contracted to provide engineering services for approximately 3 miles of 21-foot-diameter CSO storage tunnel, six (6) tunnel shafts between 75 to 140 feet deep, near surface sewers ranging from 48 to 150 inch in diameter, and multiple near surface sewer diversion & gate control structures. The project is located within the City of Cleveland along the Interstate 90 corridor from approximately Marquette Road to East 110th Street.
DST/E140/Dugway South Site Restoration03-May-1816-Aug-183rd Quarter 2019$1.5
Various post construction enhanced site restoration in accordance with the tiered restoration approach for the Dugway Storage Tunnel, East 140th Consolidation and Relief Sewer, and Dugway South Relief and Consolidation Sewer projects.
Shoreline Consolidation Sewer4th Quarter 20192nd Quarter 20202nd Quarter 2022$86.2
The Shoreline Consolidation Sewer project consists of approximately 11,700 linear feet (LF) of 114-inch-diameter sewer to be constructed along South Marginal Road from East 12th Street to its downstream connection to the Shoreline Storage Tunnel (SST) at Shaft SST-7 near Marquette Road. The SCS project will reduce the number of combined sewer overflows (CSOs) to Lake Erie by capturing and conveying CSO from seven CSO outfallsthat currently discharge to Lake Erie.
  Southerly CSO Projects        
Burke Brook Open Channel Improvements (BOCI)N/AN/A1st Quarter 2019$12.6
The Burke Brook Open Channel Improvements (BOCI) project consists of enclosing two existing open channels along I-77 that currently convey stormwater and combined sewage overflows during wet weather. The project includes the construction of approximately 1,100 feet of 78-inch to 120-inch CSO consolidation piping and restoration of surface drainage channels to carry separate storm flows draining from the surrounding area. The project is an initial phase in addressing the CSO control Measures required at this location; associated CSO control improvements will follow in a separate project under Control Measure 21 of the Consent Decree.
Southerly Tunnel1st Quarter 20212nd Quarter 20213rd Quarter 2024$276.4
The Southerly Tunnel (SOT) project includes the construction of a 23-foot diameter storage tunnel extending approximately 18,000 feet in length and controlled by the Southerly Tunnel Dewatering Pump Station (STDPS) to send dry and wet weather flows to the SWWTP.
Southerly Tunnel Dewatering Pump Station1st Quarter 20212nd Quarter 20214th Quarter 2027$30.6
The STDPS project includes the construction of a deep tunnel pump station that will dewater the Southerly Tunnel under dry and wet weather conditions. The pump station would lift flows from the deep storage tunnel to be conveyed by gravity to the SWWTP and will be roughly 80 feet deep.
SCSO-1 Burke Brook Consolidation Sewer3rd Quarter 20224th Quarter 20222nd Quarter 2024$15.2
SCSO-1 Burke Brook Consolidation Sewer
SCSO-2 Kingsbury Run Consolidation Sewer3rd Quarter 20214th Quarter 20211st Quarter 2024$69.2
SCSO-2 Kingsbury Run Consolidation Sewer
SCSO-3 Morgana Run Consolidation Sewer2nd Quarter 20223rd Quarter 20222nd Quarter 2024$29.3
SCSO-3 Morgana Run Consolidation Sewer
Pearl Road & Jennings Road Storage Tanks & Pump Station Upgrades05-Jul-1815-Nov-184th Quarter 2020$9.2
This project''s purpose is to address Control Measure #23 of the Consent Decree, which requires improved CSO control for Outfalls CSO-045 and CSO-088. To limit Regulator WR-34 and BC-05-AJB activations to 4 or less in a typical year, several improvements are planned. These include the construction of CSO Storage Tanks at Regulators WR-34 and BC-05-AJB, the modification of Regulator WR-52, the upgrade of the pumping capacity of the Jennings Road Pump Station from 3.2 MGD to 5.5 MGD, and the separation of Old Treadway Creek from the Jennings Road combined sewer (and its rerouting to the Cuyahoga River). The scope of the Jennings Road Pump Station will likely include a more extensive electrical system upgrade.
  Westerly CSO Projects        
West 3rd Quigley / Westerly Miscellaneous CSO Control20-Apr-17 A07-Sep-17 A2nd Quarter 2019$8.3
The West 3rd CSO Control project includes a storage and conveyance sewer and tank to control overflows at CSOs 082 and 089, both of which discharge to the Cuyahoga River. The projects will provide CSO control for the Typical Year control events.
Westerly Tunnel Dewatering Pump Station (C)N/AN/A3rd Quarter 2019$28.0
The WTDPS is currently planned as an 80'' diameter, 36 MGD dry pit/wet well pump station to dewater the Westerly Storage Tunnel after wet weather events.
  Easterly Plants        
Easterly Chemically Enhanced High Rate Treatment Facility02-Apr-15 A20-Aug-15 A16-Aug-18$125.0
The Easterly Chemically Enhanced High Rate Treatment (CEHRT) Facility is Consent Decree Control Measure 2. This facility must start design within 6 months of approval of the Pilot Testing Report. The Easterly CEHRT project includes preliminary design and then design of the new high rate treatment facility to treat CSO-001 based upon the findings documented in the Pilot Testing Report.
  Southerly Plants        
Southerly Optimized Parallel Treatment20-Aug-15 A04-Feb-16 A15-Nov-18$50.5
This project consists of modification to the existing treatment plant in order to accommodate parallel operation of the first and second stage aeration systems during period of high flows to meet the District’s Long Term Control Plan. This project also includes an evaluation, design and construction to protect Southerly’s infrastructure and assets during extreme wet weather events. In 2015, the District had bidding documents prepared for the rehabilitation of the main substation at Southerly. It was determined that this substation rehabilitation work should be bid with the Optimized Parallel Treatment project.
Southerly Electrical Infrastructure ImprovementsN/AN/A05-Jul-18$23.5
The Southerly Optimized Parallel Treatment (SOPT) project included a new First Stage Effluent Pump Station and Chlorine Contact Tank and plant electrical improvements. The SOPT project has been placed on hold as discussions with the District’s Consent Decree are being addressed with the US and Ohio EPA agencies. The non-SOPT electrical improvements need to be constructed. Thus, the non-SOPT electrical improvements were bundled into a new project called Southerly Electrical Infrastructure Improvements SEII/1401A. This project is to provide a new main switchgear building to provide power for SWWTC, the future Southerly Tunnel Dewatering Pump Station, and the future Southerly Tunnel boring machine; HVAC upgrades to several Southerly electrical substation buildings; replacement of the Southerly Cuyahoga Valley Interceptor (CVI) Pump Station electrical switchgear and a new motorized weir gate at the existing Big Creek Interceptor BC100 location. The existing Southerly substation will be demolished by First Energy after the new facilities are in place. A new main utility substation will be installed by First Energy under a separate contract. The SWWTC is located at 6000 Canal Road, Cuyahoga Heights, Ohio 44125. The BC100 site is located approximately 3,300 feet east of the intersection of West Shaaf Road and Van Epps Road in a field beyond the end of Van Epps Road in Brooklyn Heights, Ohio 44131.
  Westerly Plants        
Westerly Chemically Enhanced High Rate Treatment Facility03-Nov-16 A20-Apr-17 A3rd Quarter 2019$70.2
The Westerly Chemically Enhanced High Rate Treatment (WCEHRT) project includes preliminary and final design of the new high rate treatment facility. The District is required per Appendix 1 of the CD to commence design of the final facilities within 6 months of EPA approval of the Pilot Testing Report and issue a construction notice-to-proceed within 18 months of design commencement. Furthermore, the WCEHRT project was an agreed upon change during CD negotiations with EPA to the District’s original CSO control plan thus minimal planning has been done for the design of the final facilities. Considering both the aggressive implementation schedule upon approval of the Pilot Testing Report and the limited planning performed to date, advancement of the project prior to EPA approval is necessary.
.
CIP Combined Sewer Overflow Control Program (CSO) Sub-program Total $1,121.1
.
CIP Districtwide Activities
  CIP Building Improvements        
Easterly New Maintenance Building1st Quarter 20202nd Quarter 20203rd Quarter 2021$7.3
The project involves the design and construction of a new, stand alone maintenance building. The building will include new mechanical and electrical shops, weld and fabrication work area, stockroom with loading dock and centralized parts storage, and locker room and related facilities.
District Wide D/B Energy Conservation and Management Project15-Mar-18 AN/A21-Jun-18$2.5
This design-build project will evaluate, design, and implement energy conservation opportunities with a focus on energy efficiency payback at various District locations. This work shall include but is not limited to design, financial evaluation, operations and maintenance and training.
Southerly Building Heat Boiler Evaluation05-Apr-18 21-Jun-1801-Nov-18$4.1
This two-step design-build project will evaluate, design, and implement a new regional heating hot water boiler plant system to replace the existing central steam boiler system. Condensing boilers are proposed to allow them to operate at a lower temperature on mild days at a thermal efficiency above 90% and provide a redundant boiler in each plant. The existing steam boiler system is oversized, antiquated and in overall poor condition. The existing steam boilers require full time on-site stationary engineers when they are operating. The steam generating facility was originally designed to provide 450 PSIG steam for process loads, including the Zimpro thermal conditioning process and provided building heat as an ancillary function. The process steam load was eliminated several years ago, so the plant is operated to provide heat only at a significantly lower pressure of 150 PSIG.
Southerly Maintenance Building Roof Replacement20-Sep-18N/A06-Dec-18$1.8
Southerly Maintenance Building Roof Replacement
District-wide Roadway Assessemnt and Improvements06-Dec-18N/A1st Quarter 2019$1.0
District-wide Roof Evaluation and Improvements06-Sep-18N/A06-Dec-18$1.6
This project is the construction of recommended repairs/replacements over 3 years as a result of a district-wide roof assessment and the replacement of the Southerly Maintenance Building Roof. (construction only)
Easterly Roofing and Structural Improvments3rd Quarter 20214th Quarter 20211st Quarter 2023$0.2
Easterly Roofing and Structural Improvments
Easterly Screenings Building Improvements3rd Quarter 20214th Quarter 20214th Quarter 2022$0.1
Easterly Screenings Building Improvements
Southerly Maintenance Buildings Rehabiltation4th Quarter 20201st Quarter 20213rd Quarter 2022$6.3
Maintenance Building Rehabilitation includes HVAC, electrical rehab, lockers and replacement of roof.  Miscellaneous Equipment Storage Building rehab.
Southerly Site Paving Improvements1st Quarter 20212nd Quarter 20214th Quarter 2022$10.6
This project includes the replacement of the existing site paving.
Building Maintenance Repair and Renewal (2019-2036)3rd Quarter 20214th Quarter 20214th Quarter 2022N/A
Building Maintenance Repair and Renewal (2019-2036)
  CIP Districtwide        
Automation Program Management Phase-117-Sep-15 A02-Jun-16 A01-Nov-18N/A
This program will provide required upgrade and configuration of software for process control and reporting functions for compliance reporting and maintenance needs across the District. This Program will take a broad-based effort to improve control system equipment, data collection and documentation and maintainability of the control system and enhance overall system functionality and reliability. This contract will include Program Management services, programming, integration, design and CA services. In addition, Phase I will include the replacement of obsolete programmable logic controllers (PLCs) currently in operation at Westerly WWTP.
Westerly PLC ReplacementN/AN/A01-Nov-18$5.9
The primary objective of this project is to replace the obsolete programmable logic controllers (PLCs) and associated I/O distributed throughout the Westerly WWTC. Additionally, this project will replace obsolete operator interface terminals (OITs) and incorporate process improvements through application of automatic controls. HMI graphics will be updated where required to incorporate interface modifications as a result of process operational improvements.
Construction Safety and Security Services05-Apr-1817-May-18N/AN/A
Seeking services for full and part time security to be provided at active District construction sites for durations and locations as needed. Security services to provide protection and support to District personel at active construction sites as part CIP and CSO Consent Decree.
Automation Program Management Phase-204-Oct-181st Quarter 20194th Quarter 2019$21.4
Phase 2 will include the replacement of the remaining obsolete programmable logic controllers (PLCs) currently in operation throughout the District’s facilities. In addition, the remaining items identified in the Process Control and Automation System Evaluation and Master Plan will be implemented per the recommendations identified in Phase I that will further enhance the District’s control system equipment, data collection and documentation and maintainability of the control system and enhance overall system functionality and reliability.
CIP Environmental Contract02-Aug-1806-Dec-18N/AN/A
CIP Environmental Contract
Dampers / Exhaust Fans04-Oct-18N/A1st Quarter 2019$2.0
Replacement of equipment recommendations from the HVAC Equipment Assessment project.
.
CIP Districtwide Activities Sub-program Total $64.8
.
CIP Treatment Plants
  CIP Treatment Plants Easterly        
Easterly Grease Handling ImprovementsN/AN/A05-Apr-18 $2.5
Demolition of the grease reactor and associated equipment, replacement of process piping heat tracing and insulation and building improvements.
Easterly Aeration Tank Rehabilitation Improvements16-Aug-1806-Dec-183rd Quarter 2019$11.0
Clean and remove biosolids and grit from eight aeration tanks. ?Replacement of existing membrane diffusers in eight aeration tanks. Installation of NPW flushing water to each diffuser grid and to the main drainage conduit in the Aeration Gallery Buildings. Installation of motorized flushing gates in Aeration Tanks Passes 1 and 3 for cleaning tank floors. Concrete repair of aeration tanks main drainage conduit cracks and expansion joints. Installation of one new aeration tank blower in the west spare blower location in the Blower Building. Leak test aeration blower piping and make repairs. Evaluate and repair aeration blower heat exchangers.
Easterly Screenings Conveyor Belt Replacement20-Aug-1805-Nov-182nd Quarter 2019$0.8
Replacement of the existing South and North conveyor belts and East and West shuttle conveyor belts.
Easterly Southerly Sludge Pump System (2011-0017)4th Quarter 20211st Quarter 20222nd Quarter 2023$6.3
Easterly R&R Projects (2019-2036)3rd Quarter 20214th Quarter 20214th Quarter 2022N/A
Easterly Weigh Scale (design-build)4th Quarter 20211st Quarter 20224th Quarter 2022$0.6
Easterly Weigh Scale (design-build)
Easterly Electrical Service Improvements19-Jul-1806-Dec-183rd Quarter 2020$12.0
Implement recommendations from the Easterly and Westerly electrical service study ta Easterly WWTP.
  CIP Treatment Plants Southerly        
Southerly Gravity Thickener Odor Control3rd Quarter 20194th Quarter 20194th Quarter 2020$3.7
Southerly Second Stage Settling Improvements18-Aug-16 A05-Jan-17 A20-Sep-18$40.8
Evaluate and address hydraulic balance issues. Structural rehabilitation and modification to the concrete tanks, collectors, return sludge line, weirs/troughs, dewatering pumps, access building roof, polymer feed system, skimming equipment, baffle chamber, channel blowers, air compressors.
District Wide Solids Handling Study2nd Quarter 20193rd Quarter 2019N/AN/A
Evaluate solids handling at the three plants. Considerations at Easterly include sludge quality, storage, and pumping rates/pump type. Southerly considerations include odor control, Easterly sludge force main and Southerly discharge flexibility, hydrogen sulfide control and storage versus FBI capacity.
Skimmings and Decant Storage Facility Access Improvements04-Jun-1815-Oct-184th Quarter 2019$0.5
Fabricate and install catwalk spanning from DAF tanks to skimmings tanks to permit safe access to top of skimmings tanks and eliminate the need for vertical ladder improvements.
Southerly Disinfection Chemical Tank Replacement06-Sep-18N/A15-Nov-18$1.0
Evaluate 8 storage tanks and associated equipment and design/build chemical storage needs.
Southerly Grease and Skimmings Automation Relocation21-Aug-18N/A06-Nov-18$0.2
The location of two PLC enclosures on top of the DAF tanks exposes the equipment to hydrogen sulfide leading to the corrosion of electronics and hardware. There is an adjoining electrical room that houses the remaining automation equipment. It is recommended to move the automation hardware from above the tanks to the electrical room.
REF Waste Heat Boiler Economizer Rehab06-Sep-181st Quarter 20191st Quarter 2020$1.0
Southerly O&M has experienced multiple unexpected REF process shutdowns due to leaks in the Waste Heat Boiler (WHB) system on all three Fluidized Bed Incinerator trains, specifically in the WHB Economizers. This project proposes replacement of all WHB Economizer tubing to remediate the need for constant tube leak repairs.
Southerly Steam Generation/Reactor/Incineration Building DemolitionN/AN/A2nd Quarter 2020$2.0
Demolition of steam generation, reactor and incineration buildings as an outcome of the District Wide Facilities Decommissioning Study.
Southerly R&R Projects (2019-2036)3rd Quarter 20214th Quarter 20214th Quarter 2022N/A
Southerly 2nd Stage Aeration Improvements3rd Quarter 20214th Quarter 20212nd Quarter 2023$23.8
Southerly Effluent Filtration and Disinfection Improvements3rd Quarter 20224th Quarter 20221st Quarter 2024$50.1
Southerly Effluent Filtration and Disinfection Improvements
Southerly Waste Liquor Handling Improvements4th Quarter 20191st Quarter 20202nd Quarter 2021$2.0
Miscellaneous building improvements and replacement of waste liquor pumps and compressors.
Southerly Wet Stream Hg Removal3rd Quarter 20214th Quarter 20214th Quarter 2022$10.4
Southerly Primary Sludge Degrit Building Demolition2nd Quarter 20223rd Quarter 20221st Quarter 2024$1.2
  CIP Treatment Plants Westerly        
Easterly & Westerly Low Voltage Equipment Replacement01-Feb-18 A07-Jun-181st Quarter 2019$8.9
The obsolete Motor Control Centers at WWWTC and EWWTP should be replaced in their entireties under a design-build contract delivery system. This will allow the equipment to meet the District''s current safety policies, minimize the potential for equipment failure, to be the latest series from manufacturers so that certified replacement parts will be available for many more years and up to date record documents will be available for the District''s maintenance staff. Includes replacement of Westerly PEPS VFDs.
Westerly WWTC Trickling Filter Media Replacement01-Aug-1812-Dec-181st Quarter 2020$4.2
At the Westerly Wastewater Treatment Center (WWTC), wastewater is treated by a suspended growth activated sludge treatment process that utilizes three (3) circular fixed media trickling filters that stand 47 feet tall and 80 feet in diameter. Each trickling filter contains 5024 cross flow plastic media modules that provide a total of 7,717,000 square feet of surface area for biological growth. As wastewater flows over the plastic media, bacteria and microorganisms such as protozoa attach themselves to and grow on the media. This growth of biomass will convert suspended solids and dissolved solids to settable solids which are removed in final settling clarifiers. This project will replace the plastic media originally installed in 1995 based on material condition assessments and performance evaluations.
Westerly Facilities Plan05-Apr-18 19-Jul-18N/AN/A
Systematic condition assessment of Westerly''''s assets. Evaluate existing processes for optimized operation and long term functionality. Identify and develop project definitions to be prioritized for future CIP.
Westerly Grit Equipment Rehabilitation02-Aug-1806-Dec-184th Quarter 2019$1.5
Assess, rehab, and/or replace Westerly''s aging grit equipment.
Westerly Primary Sludge Rehabilitation1st Quarter 20192nd Quarter 20192nd Quarter 2020$1.0
Evaluate and replace aging Primary Sludge piping and equipment, which was installed in 1977.
Westerly R&R Projects (2019-2036)3rd Quarter 20214th Quarter 20214th Quarter 2022N/A
Westerly R&R Projects (2019-2036)
Westerly Settling Tank Mechanical Repairs4th Quarter 20201st Quarter 20212nd Quarter 2022$3.0
Rehabilitation of primary and final clarifiers ferrous materials. Some miscellaneous concrete, electrical and instrumentation work will also be required
Westerly PEPS VFD Replacement3rd Quarter 20214th Quarter 20213rd Quarter 2022$0.6
Westerly PEPS VFD Replacement
.
CIP Treatment Plants Sub-program Total $189.0
.
Non CIP Planning
Cuyahoga Valley Interceptor Local Sewer System Evaluation Study05-Oct-17 A07-Jun-18N/AN/A
This planning-level SSES project will identify Clean Water Act issues in the local sewer system tributary to the Cuyahoga Valley Interceptor, develop and evaluate alternatives, and recommend construction and maintenance projects to support member community initiatives and the District’s Member Community Infrastructure Program (MCIP) and Community Discharge Permit Program (CDPP).
.
Non CIP Planning Sub-program Total N/A
.
.
2018 - 2022 CIP Program Summary Total $1,428.4
.
Legend
(1) Dates identified with A (actual) indicates Board Authorization to Issue Request for Proposal
(2) Dates identified with A (actual) indicates Board Authorization to Enter into Consultant Agreement